Every transformer nameplate carries a code such as Dyn11. Customers regularly ask whether they need Dyn11 or Dyn5, and whether one is "better". The short answer: for a transformer feeding its own low-voltage network, neither is better. For a transformer that must work in parallel with another, or feed a network whose protection was designed for a specific phase shift, the vector group must match. Here is what the code means.

Reading the code

  • D – the high-voltage winding is connected in delta.
  • y – the low-voltage winding is connected in star (wye).
  • n – the star point (neutral) of the LV winding is brought out to a terminal, so single-phase loads and TN earthing are possible.
  • 11 or 5 – the phase displacement between HV and LV, in "clock hours" of 30°: 11 means the LV voltage leads the HV voltage by 30° (–330°); 5 means the LV lags by 150°.

Small ratings (25 and 40 kVA in the PNACHO-O series) use Yzn11: a zig-zag LV winding that tolerates unbalanced single-phase loads better and gives a low zero-sequence impedance – ideal for rural networks with many single-phase consumers.

Why both conventions exist in Europe

Dyn5 was the traditional German (VDE) standard and remains common in Germany, Austria, Switzerland and in Polish distribution networks; Dyn11 is the IEC/British convention and dominates Scandinavia, the Benelux, Southern Europe and most new industrial installations. Neither is technically superior. The 180° difference between them is only the direction in which the winding terminals are labelled – the electrical behaviour of the transformer is identical.

When the vector group really matters

SituationRequirement
Single transformer feeding its own LV networkAny vector group – choose the grid operator's preference
Two transformers in parallel on the LV sideIdentical clock number (both 11 or both 5), same ratio, uk within ±10 %
Replacement of an existing unitSame vector group as the old one, unless the LV network is rewired
Differential protection across the transformerRelay settings must match the phase shift
PV or battery plantAs specified by the grid operator's connection conditions

Connecting a Dyn11 and a Dyn5 unit in parallel produces a 180° phase opposition between their LV terminals – a direct short circuit through both transformers. Always check the clock number before paralleling.

How PNACHO transformers are supplied

All PNACHO-O and PNACHO-D units from 63 kVA are Dyn11 as standard and Dyn5 on request at no extra cost; 25 and 40 kVA are Yzn11 (Yzn5 on request). The vector group is confirmed by the routine test (ratio and phase-displacement measurement, IEC 60076-1) and printed on the nameplate. Tell us the operator's connection conditions or the nameplate of the unit you are replacing, and we deliver the matching group.

vector groupDyn11Dyn5Yzn11parallel operation
Share this article

Request a quote for your PNACHO transformer

Send us rated power, voltages and the site of installation – our engineers will select the right configuration and send a quote within 24 hours.

See the range